Summary: High-pressure gas installation

Services Supplied

Science Laboratory Installation

Project Outline

Following a period of rapid growth, Quantum Science Ltd decided to relocate their laboratory to improve efficiencies in the working environment with the scope to grow in the future. At Techspace One in Daresbury, the newly built premises offered a blank canvas to design and install a purpose-built laboratory bespoke to their needs within a ten-week project timescale.

Scope of works:
  • Supply and install five Nitrogen 5.0 Purity single bottle distribution manifolds with safety relief systems, bottle support, high-pressure flexible hoses and two 0-2 bar regulators, two 0-4 bar regulators and a 0-10 Bar regulator.
  • Extend the 15mm degreased copper pipework supply from the new gas manifolds to the required locations within the laboratory with the necessary regulators needed by the end user.
Higgins laboratory high pressure gas lab installation
Higgins lab gas engineers high pressure
  • Supply and install a new powder-coated gas bottle cage.
    Extend the existing site Nitrogen supply to the required position.

  • Supply and install a new Nitrogen manifold with three 0-2Bar 5.0 Purity Lab Master LGB5000 Series outlet point regulators and one 0-4Bar 5.0 Purity Lab Master LGB5000 Series outlet point regulator.
  • Extend the existing site Compressed Air supply to the required point and supply and install a new Compressed Air outlet regulator with 60-80 PSI.
  • On completing the work, a written scheme of examination and test certificates shall be provided for each of the four new gas systems.
Higgins-laboratory-plumbing-techspace-one-1
Higgins laboratory gas installation cheshire
Higgins laboratory Mechanical Cheshire
Higgins laboratory regulator fitting runcorn

Meel Group Lab Gas Expertise

Adherence to regulations: Meeting all industry regulations, including CDM, Pressure Systems Safety Regulations 2000 (PSSR), British Compressed Gas Association (BCGA) Codes of practice, Gas Safe, and WRAS.

“We were pleased with the end results of the installation and found Meel Group Building Services a good company as a supplier. We are currently working with them on other projects as part of our labs’ expansion plan.”

Cong-Duan Vo, PhD

CTO